Capital Projects Division

JACKSON

Heating Systems Renovation

This project involves repair, replacement or upgrade of existing space and/or domestic hot water heating systems at the development, with technology solutions suitable for the specific site conditions and budget available. The project will also include associated electrical and plumbing work as needed. The detailed scope of work is determined based on engagement of stakeholders and the specific design for the site.


Data updated as of November 21, 2022



Planning
100% Complete
Procurement
100% Complete
Design
96% Complete
Construction
16% Complete

Project Delivery Type: Design Build



Project Update
Design and construction activities are both in progress, with early design packages completed and progressing to construction.

Project Timeline

Planning

Planned Start Date: October 2019
Actual Start Date: October 2019
Planned End Date: December 2019
Actual End Date: December 2019

Procurement

Planned Start Date: January 2020
Actual Start Date: January 2020
Planned End Date: February 2022
Actual End Date: February 2022

Design

Planned Start Date: January 2022
Actual Start Date: January 2022
Planned End Date: August 2022
Current Estimated End Date: November 2022

Construction

Planned Start Date: April 2022
Actual Start Date: April 2022
Planned End Date: January 2024
Current Estimated End Date: February 2024

Project Budget

Estimated Budget: $34.13 million
Funding Sources: Federal, State


Location

3080 Park Avenue
Bronx, NY, 10451


Project Staff

Project Contact: Mark Sadowski
Contact NYCHA about this project.





The data shown on this site is accurate as of the date shown above, and is updated every two weeks. While the data comes from NYCHA’s project management system, only a subset of capital projects are currently presented here. Excluded projects including: projects for which funds are not yet available to NYCHA, projects for which detailed schedules have not yet been developed by NYCHA, projects completed before 2017, emergency projects, projects which are funded and implemented across more than one development, Local Law 11 façade inspections and related construction, and project records with data quality issues. Projects undertaken as part of the Superstorm Sandy recovery and storm resiliency efforts are also excluded from this site; details about these projects can be found at NYCHA Recovery & Resilience.

In addition, planned start and end dates shown for each project may reflect schedule re-baselining undertaken as per NYCHA internal policies, rather than the original schedule developed for that project. All changes in projects schedules, estimated budgets and funding sources may not be fully reflected. Construction phase dates and progress shown for projects incorporates pre-construction preparation activities, not only physical construction, and project completion is define as 100% physical construction completion excluding additional project closeout activities that may be required. As a result of these and other limitations, the Capital Projects Tracker is not an analysis tool and the data should not be used for quantitative analyses. It is intended to be used for stakeholder information purposes only.