The primary scope of work for this project is Elevators. Projects in this scope area may include: replacing or upgrading one or more elevator cabs; installing new machine motors, rails, hydraulics, and/or cables; repairing and/or replacing structure and walls in elevator pit and shaft; installing new sliding ADA (Americans with Disabilities Act) accessible car doors; installing car frames, enclosures, flooring, hoist ways, and lighting; installing mainline power switches, breakers, and feeders to controller, underground and/or buried piping, and emergency power plant, controls, and indicators; and installing Remote Elevator Monitoring System (REMS) and connection to BMS (Building Management System). The full, detailed scope of work for this project including any additional work areas will be updated here after alignment with project stakeholders through scoping and design activities.
Data updated as of December 04, 2023
Project Delivery Type: Design Bid Build
Project Update
Construction is in progress, with regular updates to stakeholders during progress meetings and through other channels, and ongoing coordination to minimize disruption on the property. Regular site management, safety, quality, and environmental (where relevant) monitoring activities are being undertaken by the project team and other, independent NYCHA teams and/or 3rd party consultants. Project TimelinePlanning
Planned Start Date: July 2017 Design
Planned Start Date: August 2017 Procurement
Planned Start Date: December 2020 Construction
Planned Start Date: September 2021 Project Budget
Estimated Budget: $28.03 million |
Location
41-01 12th Street Project Staff
Project Contact: Robert Mitchell |
The data shown on this site is accurate as of the date shown above, and is updated every two weeks. While the data comes from NYCHA’s project management system, only a subset of capital projects are currently presented here. Excluded projects including: projects for which funds are not yet available to NYCHA, projects for which detailed schedules have not yet been developed by NYCHA, projects completed before 2017, emergency projects, projects which are funded and implemented across more than one development, Local Law 11 façade inspections and related construction, and project records with data quality issues. Projects undertaken as part of the Superstorm Sandy recovery and storm resiliency efforts are also excluded from this site; details about these projects can be found at NYCHA Recovery & Resilience.
In addition, planned start and end dates shown for each project may reflect schedule re-baselining undertaken as per NYCHA internal policies, rather than the original schedule developed for that project. All changes in projects schedules, estimated budgets and funding sources may not be fully reflected. Construction phase dates and progress shown for projects incorporates pre-construction preparation activities, not only physical construction, and project completion is define as 100% physical construction completion excluding additional project closeout activities that may be required. As a result of these and other limitations, the Capital Projects Tracker is not an analysis tool and the data should not be used for quantitative analyses. It is intended to be used for stakeholder information purposes only.
The Capital Projects Tracker works best on the following web browsers: Chrome 93 or later, Edge 93 or later, Firefox 93 or later, and Safari 15.2 or later. This site is not fully language or web accessible due to technical constraints; these areas will be enhanced in future site updates.